2026 Miscellaneous Road Repairs and Overlays

The 2026 Miscellaneous Road Repairs and Overlays Project is comprised of approximately 2.5 miles of local and collector streets, .9 miles of local trails and rehabilitation of the Bunker Hill Park parking lot within the City of Lakeville. This project generally includes pavement milling and overlay, partial curb replacement, spot sidewalk replacement, ADA pedestrian ramp updates, watermain corrosion protection and minor storm sewer repairs.

Helpful Information

  • Phasing map (PDF)
  • FAQs

Project Timeline

  • August - October 2025: Preliminary engineering
  • Winter 2025/2026: Final design
  • February 26, 2026: Receive and publicly open bids
  • March 5 2026: Neighborhood meeting
  • April 6, 2026: City Council to review bids and consider award of contract
  • April-June 2027:Construction
    • Note: Schedule subject to change, more details will be posted on this webpage when available

Private Features Within City Right-of-Way

  • Lawn irrigation or sprinkler systems
  • Pet containment systems
  • Landscaping and plantings

If you wish to protect private features from damage during construction, please temporarily remove them from the City right-of-way. City staff will mark areas of anticipated excavation with white paint and flagging. See the video below for more details.

Neighborhood Meeting

March 5, 2026
4:30-6:30 p.m.
Lakeville Water Treatment Facility
18400 Ipava Avenue

Project Newsletters

Read through all project updates in our Archive Center.

Contact Us

If you have any questions regarding the project, contact Jake Johnson, Senior Construction Representative, at 952-985-2794 or by email.